For the ninth time .. Blow up gas pipeline in El-Arish .... "We will not allow Israel to export our wealth" message on the sand of the bombers


For the ninth time at dawn by unidentified masked natural gas line to reality after 17 kilometers west of El-Arish, where the flames rose to a distance of 30 meters and see the flames from a distance of 40 km

Company officials were able to close the valves of the GASCO key to control the flames and left suicide message which is written on the sand will not allow the export of our wealth to Israel. She preview the initial site of the blast that the perpetrators have targeted gas pipeline depth of two meters away every hole on the other a distance of 50 meters and placed three explosive devices in every hole and detonated bombs remotely detonated two bombs, while the third did not explode and fled to the mountainous areas.
A security source said an official in northern Sinai that all the main stations of the gas has been secured in full and provide them with surveillance cameras, but the culprits this time changed their strategy of bombing targeting the same line and not the stations and this line extends for a distance of hundreds of kilometers Sinai desert and difficult to control security, and pointed out that in the period earlier been arrested nearly 60 people accused in the bombings, but there are some who are still on the run from their bombing campaign and confirmed that the security continues to catch them, especially after it was agreed to information identifying their personality through investigations carried out with the defendants arrested today.
For his part, Major General Abdul Wahab Congratulations Governor of North Sinai to blow up gas pipeline resulted in a stopped pumping gas source for some states as well to stop the supply of the industrial area in central Sinai and the plant steam and more than five thousand home town of El Arish in the context began prosecution Arish under the supervision of Chancellor Nasser Numba lawyer the first year of the North Sinai Prosecutions to investigate the bombing of the gas pipeline ... Which occurred in the area of ​​the field 17 km west of El-Arish ... Where a team of prosecutors moved to the area to inspect the site of the blast.
The prosecution decided to form a committee from the Ministry of Petroleum to determine the losses and the valuation of damages. The assignment of the bomb squad to display and knowledge of the material used and sent to the criminal lab to determine its quality.
As well as the line to call the guard asked, and listening to witnesses ..
And demanded the CID investigation on the incident quickly and intensify efforts to adjust the speed of the accused.
Said Magdy Tawfiq, head of the Egyptian Company for Natural Gas (GASCO) that the working group has Bjasco immediately after the incident isolation of the bombing and secure the scene and by closing valves before and after the blast site to prevent access to gas.
He explained that the working group has been able to control the fire was extinguished at about quarter to six in the morning.
He added that the bombing led to the suspension of the supply of natural gas to homes and Arish power plant, cement plants and stopped all work Tdwia gas for export.